Gwonseon Juwoon Reconstruction "Resolution Invalidation" Trial Postponed
[Breaking News] As the Gwonseon Juwoon (1st and 3rd phases) reconstruction project faces hefty compensation disputes, the first trial regarding "resolution invalidation" scheduled for the 26th has been postponed to July 3rd (see Suwon Ilbo, June 25th at www.suwonilbo.kr).
Of the 12 shopping complex union members who filed the lawsuit, 9 have expressed their intent to withdraw the case after accepting the court's mandatory conciliation decision in the preceding trust registration and eviction claim lawsuits.
According to Suwon District Court and the Gwonseon Juwoon Reconstruction Union, the 12 shopping complex members filed a confirmation lawsuit on January 11th of last year seeking to invalidate the reconstruction resolution, stating they could not consent to the reconstruction project covering approximately 96,056 square meters in Gwonseon-dong, 1067-1 lot.
At the scheduled first trial on the 26th, when 9 members of the reconstruction union stated they would accept the court's mandatory conciliation decision in the trust registration and eviction claim lawsuit that could affect this case, a request for resumption of arguments was submitted for July 3rd.
An official from the Gwonseon Union explained the postponement, stating: "As the 9 members have accepted the court's conciliation, we will proceed with arguments after carefully reviewing the settlement agreement in court proceedings and its legal implications."
Previously, the court panel had seen the Gwonseon Union and shopping complex union engage in seven rounds of marathon negotiations, but after failing to reach consensus, the court proceeded with mandatory conciliation on the 26th of last month. The court decided to compensate the 12 members with 600 million to 1.8 billion won per person, totaling 9.51 billion won, and to lend 200 million won per person for relocation.
Subsequently, the shopping complex union submitted an objection, claiming the compensation (their original demand totaled 25.4 billion won) is insufficient. In particular, some shopping complex members pursuing litigation are demanding increased compensation and relocation allowances, guarantee of 133% ownership stake (compared to the contractor's proposed 118.02%), and separate building assignments.
Meanwhile, the Gwonseon Union received project implementation approval in March 2005 and is constructing Daelim e-Pyunghansesang with 1,754 units (35 buildings, 1 basement level to 15 floors above ground) in the reconstruction of Juwoon 1st and 3rd phases in Gwonseon-dong, Gwonseon-gu, covering approximately 96,056 square meters. Construction began at the site in October last year, but is proceeding as half-finished work, excluding some commercial areas (2,464 square meters).
The 12 shopping complex members who initially agreed to the reconstruction project filed a "resolution invalidation" lawsuit at Suwon District Court on the same month, followed by a "construction prohibition preliminary injunction" petition on the 19th. In March of the same year, the court accepted the shopping complex union's petition for construction prohibition preliminary injunction.
Unable to find a breakthrough, the additional burden of project delays, seven rounds of design change consultations, and lawsuit proceedings costs are being passed entirely to the union members (1,181 members).
In particular, the monthly interest loss alone due to escrow and lawsuit proceedings amounts to 422 million won for union members' payments to financial institutions. Union members must bear at least 20 million won or more in additional costs annually. Some are pointing out that the shopping complex union's sudden reversal after initially agreeing to the reconstruction project may constitute "land banking."