Hyun Geun-taek, Suwon Deputy Mayor, Inspects Key Projects and Conducts Field Administration
[Suwon Ilbo=Correspondent Jung Jun-sung] Hyun Geun-taek, Deputy Mayor of Suwon Special-status City, visited key project sites on the 6th including the Suwon resource recovery facility, resource circulation center, and Hwangguji-cheon public wastewater treatment facility in succession to check business progress and actively engage in field administration.
First, he visited the resource recovery facility to inspect the progress of the relocation and improvement project. The resource recovery facility relocation project will continue until June 2032. An interim report meeting for preliminary survey and site selection will be held in November, and the "preliminary survey completion and site selection committee" is scheduled to be established in March next year. The improvement project will progress until 2027, with plans to announce the improvement project bid in November.
The resource circulation center sorting facility construction project will proceed until December 2027. From November 2025 to April 2026, "basic and detailed design consulting" will be completed, and construction is scheduled to begin in April 2026.
The Hwangguji-cheon public wastewater treatment facility is currently undergoing comprehensive trial operations with water quality monitoring. The upper sports and convenience facilities are under construction.
Deputy Mayor Hyun Geun-taek stated, "We will regularly visit and inspect major projects to ensure they proceed without delay, and actively gather citizen opinions."