Gyeonggi Province's Frequent Design Changes Send Construction Costs 'Snowballing'
Gyeonggi Province has increased construction costs by approximately 60 billion won through design changes in various projects including roads, buildings, and rivers over the past three years.
On the 20th, Rep. Kim Hak-jin (Hannara Party, Goyang District 7) of the Gyeonggi Province Council analyzed data submitted by the Gyeonggi Province Construction Headquarters, revealing that among 48 projects conducted from 2006 through September of this year, design changes were made a total of 74 times.
According to this analysis, road construction saw 28 design changes with construction costs increased by approximately 4.86 billion won, building projects had 33 design changes with a 1.01 billion won increase, and river projects had 13 design changes with a 130 million won increase.
Notably, the road expansion and paving project between Cheongbuk and Godeok saw the initial budget of 2.08 billion won increase to 3.79 billion won through two design changes, while the road expansion and paving project between Bansong and Giheung saw costs increase by 540 million won through two design changes, with a total budget of 2.7 billion won allocated.
Additionally, the Next-Generation Convergence Technology Center project saw construction costs increase from 8.85 billion won to 9.39 billion won through two design changes, and the Gyeonggi Province Museum of Art had 1.5 billion won added to the original 1.27 billion won budget through two design changes, totaling 1.42 billion won spent.
Rep. Kim stated, "While design changes due to cultural heritage surveys and fluctuations in material prices are understandable, frequent design changes based on reasons with relatively limited justification are problematic. We must conduct thorough preliminary investigations and analyses of design, construction, and completion to ensure project credibility and transparency."