Seoho Stream Environmental Improvement Project 'On Track'

Phase 2 completion set for end of this month, project to conclude in June next yearStream width expanded to 50m, expected to prevent flood damage

By June next year, the Seoho Stream environmental improvement project will be completed.

According to the city, since 2003, the city has been receiving 22.2 billion won in budget support from Gyeonggi Province to carry out disaster prevention and create eco-friendly stream conditions in the areas surrounding Seoho Stream. The project is improving a 2km section of stream from Seodun-dong (Seodun Bridge) to Pyeongdong (Pyeonggyo Bridge) in Gwonseon-gu.

The city already completed the first phase of 0.8km section (Sudun Bridge to Nongdae Bridge) in October 2005, and is now finishing the second phase section from Nongdae Bridge to Pyeonggyo Bridge, spanning 1.2km. The current construction progress rate stands at 90%.

All Phase 2 construction is scheduled to be completed and ready for opening by the end of this month, including the installation of a temporary bridge in front of Seoho Middle School and stacking of landscaping stones on the 180m lower embankment at the lower part of Seongjagyo Bridge.

The city plans to complete landscaping work for the entire Seoho Stream environmental improvement project and organize the high water embankment area from April to June next year.

As a result, the city expects the stream width to be expanded from the existing 30m to 50m, making it possible to prevent flood damage. Additionally, it is anticipated that convenience will be provided for students commuting from near Seoho Elementary School to Seoho Middle School.